Conditions as of Wednesday, August 19, 2009:

All-terrain Vehicle (ATV) Trails

Work continues on upgrading the wetland crossings on a 1.1-mile section of trail from Wildcat Road heading west. This section of trail will be closed during the week for construction. The trail will open by 4 p.m. each Friday for weekend riding. We expect to complete this work by the end of August. This will likely be the last trail project until next spring.

An example of a recently upgraded section of trail can be found North of the Highway 54 parking lot to Bartos road. These projects will protect the long-term sustainability of the trail system and lessen the frequency of trail closings due to large rainfalls. Over the course of the next two years we hope to upgrade all wetland crossings on the property.

The entire trail system has been groomed within the last two weeks and trails are in good condition.